How Long Do Elevator Permitting & Equipment Lead Times Take in Illinois?

We work with building owners on a wide range of elevator projects across Illinois, and one of the first questions we hear is how long the work will take. The answer depends on more than the installation itself. 

Permitting, equipment lead times, engineering, site preparation, approvals, and inspections can all affect the schedule.

In this guide, we break down how long elevator permitting, equipment lead times, installation, and final inspection typically take, what can affect those timelines, and why starting early can give you more flexibility when planning your project.

Understanding Permits, Equipment Lead Times & Installation

An elevator project has three major areas that need to be coordinated from the start:

  • Permitting: Determines what approvals are required before work can begin. The process depends on the building’s location, type of work, and the authority responsible for the project.
  • Equipment: Lead times include more than manufacturing and delivery. Equipment may need to be specified, engineered, approved, manufactured, and shipped before it reaches the job site.
  • Installation: Happens once the necessary approvals, equipment, and site preparation are in place. The schedule also needs to account for building operations and other trades working on the project.

These stages can overlap, but they are also connected. A delay in one stage can affect everything that follows, which is why it helps to consider the full project timeline from the start.

How Long Does an Elevator Permit Take in Illinois?

There is no single permit timeline for every elevator project in Illinois. The process can vary based on the building’s location, project scope, type of elevator work, completeness of the submission, and whether additional information or corrections are required.

Illinois requires a permit for an alteration or new installation of a conveyance or lift device. For municipalities that operate their own approved elevator programs, permits are handled locally. In other areas, the Illinois Office of the State Fire Marshal handles the permit.

The first step is to confirm which authority handles your project.

Elevator Permits in Chicago

Chicago has its own elevator permitting process through the Department of Buildings Elevator Bureau.

There is no published turnaround for an elevator permit. The timeline depends on the project and how complete the submission is, and corrections or requests for more documentation can extend the review. A complete, straightforward submission is often issued within a few weeks, but projects that also require a building permit for structural or major electrical work add a separate review on top of the elevator permit and can take considerably longer.

Start the permitting process early rather than waiting until the installation date approaches.

Elevator Permits Outside Chicago

Permit requirements and timelines vary by municipality.

Some Illinois municipalities run their own elevator safety programs and set their own review times, often a few weeks for a complete application. In other areas, the Office of the State Fire Marshal handles permitting directly. There is no single statewide processing time, so the same project can move at very different speeds depending on the address.

If you are working on multiple properties, do not assume the same process or timeline applies to every location. Confirm the requirements for each project before submitting plans.

Elevator Permits in Northwest Indiana

Northwest Indiana follows Indiana, not Illinois, requirements.

Indiana handles elevator permitting, licensing, and inspections through its own state system, and does not publish a standard processing time. The permitting steps and contractor licensing need to be checked separately, because a process that applies to an Illinois property may not apply across the state line.

What Can Delay an Elevator Permit?

Permit review can take longer when the submission requires corrections, clarification, or additional documentation.

Common causes include:

  • Incomplete project information
  • Missing or inconsistent drawings
  • Changes to the project scope
  • Equipment specifications that have not been finalized
  • Additional structural or architectural review
  • Code requirements identified during review
  • Documentation that does not match the proposed work

Illinois is also currently experiencing longer-than-normal processing times following the transition to a new elevator safety software system, according to the Office of the State Fire Marshal. The agency advises applicants to expect delays during the transition.

Potential delays are another reason to confirm current processing conditions rather than building a schedule around an old estimate.

How Long Does it take to get Elevator Equipment?

Equipment lead times can account for a significant portion of an elevator project’s schedule.

Elevator equipment is often manufactured or configured for a specific project. Controllers, door operators, hydraulic equipment, fixtures, traction equipment, and other components can have different production schedules.

The equipment, therefore, needs to be considered early, especially if a project has a fixed completion date.

When Does the Equipment Lead Time Start?

Equipment lead time does not necessarily begin when the contract is signed.

Before manufacturing can begin, the project may go through an engineering and submittal process. Submittals establish the technical details needed to manufacture and install the equipment, including layouts, power requirements, control specifications, fixture selections, cab signals, hoistway dimensions, and other project-specific requirements.

A simplified sequence looks like this: Project scope → Equipment selection → Engineering and submittals → Approval → Manufacturing → Delivery

If a decision is still open or a submittal needs to be revised, manufacturing may not be able to begin. That is why the time between signing a contract and receiving equipment can be considerably longer than the manufacturer’s stated production lead time.

Typical Elevator Equipment Lead Times

Actual equipment lead times vary by manufacturer, equipment type, specifications, availability, and current production schedules. Use the ranges below for planning, then confirm current figures before committing to a date.

ComponentTypical lead time
Controller8 to 16 weeks
Door operators6 to 12 weeks
Hydraulic power unit6 to 12 weeks
Hall and cab fixtures6 to 12 weeks
Custom cab interiors12 to 20+ weeks
Traction equipment12 to 20+ weeks

Custom or project-specific equipment can require additional time. If a component has a longer manufacturing schedule, identifying that early gives the project team more opportunity to adjust the plan.

Ordering components through separate channels can also add time. When the controller, fixtures, wiring, and hydraulic components come from unconnected sources, a project can stall on the one item nobody specified.

How Timelines Differ by Elevator Project

The factors above apply to elevator projects generally, but the timeline can look very different depending on what you are actually doing.

Elevator Modernization

Modernization involves upgrading or replacing components in an existing elevator system.

Depending on the scope, modernization upgrades may include the controller, door equipment, machine, hydraulic equipment, fixtures, wiring, or other major components. In our experience, a single modernization typically takes several weeks for installation, with the exact duration depending on scope.

The overall project can take considerably longer than the installation because planning, engineering, equipment procurement, permitting, approvals, and site preparation occur before the elevator is taken out of service.

Existing building conditions can also affect the schedule. The condition of the hoistway, pit, machine room, electrical systems, and other components may change the scope once the project is assessed.

Elevator Installation

An elevator installation has a different set of scheduling considerations.

In new construction, the elevator needs to be coordinated with the building’s design and construction. Hoistway dimensions, pit requirements, machine room or machine space requirements, electrical service, structural work, and other building systems must be incorporated early.

Equipment selection should therefore happen early enough for the architectural, structural, mechanical, and electrical teams to design around the elevator requirements.

New installations also involve both permit tracks, the elevator permit and the building permit, so the longer of the two review processes applies from the start.

The elevator can also be integrated into the broader construction schedule. A delay in equipment, site preparation, or installation can affect other trades and potentially the building’s planned completion.

Elevator Repair, Replacement, or Major Alteration

Repair, replacement, and alteration projects can vary significantly in scope and timeline. Elevator repair timelines can range from relatively short repairs to more involved work that requires replacement parts, permits, or changes to the existing system. 

A routine repair may take much less time than replacing a major component or completing a full modernization. The timeline depends on the issue, the equipment or parts required, permitting requirements, and how the work affects the existing elevator system.

For that reason, a project-specific assessment is more useful than applying a single timeline to every type of elevator work.

What Can Delay an Elevator Project?

Permitting and equipment are major parts of the schedule, but they are not the only sources of delay. Other common causes of delay include:

  • Scope changes made after engineering or equipment approvals
  • Site not ready when the installation crew is scheduled
  • Owner or board approvals taking longer than expected
  • Equipment arriving late, or the building not ready to receive it
  • Heavier permit volume during spring and summer filing season
  • Inspections and turnover left to the end of the schedule

Finalizing the scope early, confirming the site and approvals, and scheduling inspections up front are the simplest ways to keep these from compounding into months. If an elevator fails inspection, the required repairs and reinspection can add time before the elevator returns to service.

Why You Should Start Planning Early

Starting early does not mean every elevator project takes a year. It means giving the project enough time to account for the factors that can affect the schedule.

Delays also compound rather than sitting side by side. A two-week permit correction delays the submittal approval date, which delays the manufacturing slot, which delays installation into the next available crew window. A modest delay early in a project regularly becomes a month or more by the time it reaches the installation date.

Starting early gives building owners more time to:

  • Assess the existing elevator
  • Define the project scope
  • Determine permitting requirements
  • Compare equipment options
  • Complete engineering and submittals
  • Account for equipment manufacturing
  • Prepare the site
  • Coordinate with other contractors
  • Schedule inspections
  • Plan around building operations

It also gives the project more flexibility when something changes. If a permit requires corrections, there may still be room in the schedule. If equipment has a longer lead time, the project team has more time to evaluate options. If site preparation requires additional work, that work can be scheduled before the installation crew arrives.

Waiting until the desired installation date is closed removes much of that flexibility.

Working Backward From Your Target Date

One of the simplest ways to plan an elevator project is to start with the date you want the elevator operating and work backward.

For example, if a modernization needs to be completed by June, the planning process should begin months before the elevator is scheduled to go out of service.

A sample schedule could look like this:

  1. August or September: Complete the site assessment and define the scope.
  2. October: Review and approve the proposal.
  3. November and December: Complete engineering and equipment submittals.
  4. December through March: Manufacture equipment while permitting and site preparation move forward.
  5. March through May: Complete installation.
  6. May or June: Complete testing, inspection, and turnover.

This is an example, not a guaranteed timeline. The actual schedule depends on the project type, equipment, jurisdiction, approvals, and site conditions.

The point is to start far enough ahead that permitting, equipment, installation, and inspection do not become separate scheduling emergencies.

Plan Your Elevator Project Before You Need It

Permits, equipment lead times, and installation are all important parts of an elevator project’s schedule. Waiting until an elevator is out of service or a construction deadline is approaching can leave fewer options for addressing delays.

Starting early gives building owners more time to evaluate existing equipment, determine the right scope, navigate permitting, select equipment, and coordinate installation. Explore elevator services by industry to see how project needs can vary by building type.

We can help you understand the requirements and build a realistic project timeline. Contact us to discuss your project and determine when you should get started.

iStock 621933292

Traction vs. Hydraulic Elevators: Choosing the Right System for Your Building

Choosing the wrong elevator system is an expensive mistake. A mismatch between your building’s needs and the system installed leads to higher energy costs, performance limitations, and maintenance headaches that compound over time.

Both traction and hydraulic elevators are proven technologies. Used in the right context, each one performs well. The decision comes down to what your building actually demands.

This guide covers how each system works, where each one fits best, and how they compare across the factors that matter most to building owners: height, speed, energy use, cost, and maintenance.

What Is a Traction Elevator and How Does It Work?

A traction elevator uses an electric motor to drive steel ropes or belts looped over a grooved pulley called a sheave. When the motor turns, the ropes move, and the cab travels up or down.

Attached to the opposite end of those ropes is a counterweight, sized at roughly half the cab’s maximum load. That counterweight does a significant share of the work, so the motor only manages the difference in load rather than lifting the full weight of the car and its passengers. This is what makes traction systems efficient in tall, busy buildings.

Two main drive configurations:

  • Geared traction: A gearbox sits between the motor and the sheave, reducing output speed. Cost-effective for mid-rise buildings, typically up to about 20 stories.
  • Gearless traction: The motor connects directly to the sheave with no gearbox. Faster, smoother, and the standard choice for high-rise buildings.

Machine room considerations:

  • Traditional traction: Requires a dedicated machine room at the top of the hoistway for the motor, controller, and drive equipment.
  • Machine-room-less (MRL): Components are relocated into the hoistway itself, reducing footprint and offering more architectural flexibility. Accessible maintenance provisions within the shaft are still required.

What Is a Hydraulic Elevator and How Does It Work?

A hydraulic elevator uses fluid pressure to move the cab. A hydraulic pump pushes oil into a cylinder, which drives a piston upward and lifts the car. To descend, fluid releases back into a reservoir, and the cab lowers under its own weight.

The machine room sits at ground level or in a basement adjacent to the shaft, not above it. Simpler mechanics mean fewer failure points and a lower upfront cost, which is why hydraulic systems are common in low-rise buildings.

Three hydraulic configurations:

  1. Conventional: An in-ground cylinder drilled below the pit. Smooth and stable ride, but requires excavation.
  2. Hole-less: Telescoping pistons mounted above ground on either side of the cab. Practical for sites with high water tables or environmental restrictions.
  3. Roped hydraulic: Cables combine with the piston to extend travel distance and reduce required cylinder length. A middle ground between conventional hydraulic and traction.

One important clarification: hydraulic elevators do not use counterweights. The piston lifts the cab’s full weight on every upward trip. This is the primary reason hydraulic systems use more energy than traction systems, especially in heavily used buildings.

Traction vs. Hydraulic Elevators: A Side-by-Side Comparison

Neither system wins across every category. The right fit depends on your building’s specific demands. Here is how the two compare across the factors that matter most.

Building Height

Hydraulic elevators are designed for low-rise buildings, generally up to five or six floors. Traction elevators have no meaningful ceiling height. Geared configurations handle mid-rise applications comfortably; gearless systems are the standard for high-rise towers of any height.

Speed

Traction elevators are significantly faster; geared systems travel between 100 and 350 feet per minute. Gearless systems used in high-rise buildings can reach 2,000 feet per minute or more. Hydraulic elevators generally top out around 150 feet per minute, which works for a low-rise building but becomes a bottleneck in any environment where volume matters.

Energy Efficiency

Traction systems are more energy-efficient, particularly those with regenerative drives that capture energy during descent and return it to the building’s electrical system. Hydraulic systems push against the full cab weight on every ascent. In light-use buildings, the difference is manageable; in busy buildings, it adds up over time.

Installation Cost

Hydraulic systems are generally less expensive to install. Simpler equipment, lower infrastructure requirements, and no overhead machine room. Traction systems involve more sophisticated components and a higher overall project cost. The gap between the two can be significant depending on building type and configuration.

Maintenance Requirements

Both require regular professional maintenance, but the work differs:

  • Hydraulic: Fluid and seal inspections to prevent leaks and maintain consistent pressure.
  • Traction: Rope tension checks, sheave inspections, brake testing, and motor maintenance.

Overall maintenance costs for either system are broadly comparable. What matters is that the right service agreement is in place from the start.

Machine Room Needs

Traditional traction systems need an overhead machine room, which must be planned into the building design. Hydraulic systems require a ground-level or basement equipment room, generally easier to accommodate. MRL traction configurations have reduced this difference, though maintenance access within the hoistway is still required.

Traction systems generally outperform hydraulic systems in high-rise and high-traffic environments. Hydraulic systems offer real cost and simplicity advantages in low-rise settings. 

Keep in mind, there is no universal winner; it all depends on your building.

When a Traction Elevator Is the Right Choice

Traction is the right direction when a building’s demands exceed what a hydraulic system is designed to handle. These are the building profiles where traction is almost certainly the appropriate system.

Mid- to High-Rise Buildings

Once a building exceeds five or six floors, hydraulic systems are no longer a viable option. Traction systems have no comparable limitation. Geared systems handle mid-rise applications well; gearless systems handle anything taller without compromise.

Buildings with Heavy Daily Traffic

High-traffic environments need elevators that can run continuously without performance degradation. Commercial office buildings, hospitals, hotels, and mixed-use developments all fall into this category.

Traction systems, particularly gearless configurations, are engineered for exactly this kind of demand. They maintain consistent speed and ride quality across hundreds of daily cycles in a way that hydraulic systems are not designed to match.

Properties Where Energy Efficiency & Ride Quality are Priorities

Modern traction systems with regenerative drives capture energy during descent and feed it back into the building’s electrical infrastructure. Over the system’s lifespan, this produces meaningful utility savings.

Ride quality is also a factor in premium residential buildings, corporate environments, and hospitality properties. Gearless traction systems deliver a noticeably smoother, quieter experience than hydraulic systems.

The trade-off: Traction systems require a larger initial investment, more complex installation, and additional infrastructure planning. For the right building, that investment pays off. For a low-rise building with light traffic, it often does not.

When a Hydraulic Elevator Is the Right Choice

Hydraulic elevators are not the lesser option. They are the right option for specific building types and, in those contexts, offer real advantages.

Low-Rise Buildings

For buildings up to five or six floors, hydraulic systems are a well-established, reliable choice. The travel distance fits their design, installation is straightforward, and the cost is lower than a traction system. Most low-rise residential, small commercial, and light-use office buildings fall into this category. For buildings taller than six floors, traction is the more appropriate long-term solution.

Buildings Without Existing Shaft Infrastructure

When a building does not have a shaft configured for traction, adapting to one can require significant structural changes or prove infeasible. Hydraulic systems are more flexible: the machine room can be positioned at ground level or below grade without overhead requirements, simplifying both retrofits and new installations.

Projects with Tighter Budgets

When capital cost is a primary constraint, hydraulic systems provide a path to a safe, code-compliant elevator at a lower initial investment. For building owners who need reliable vertical transportation without the overhead of a traction system, the cost advantage is a legitimate and practical reason to go hydraulic.

Cost Considerations When Choosing an Elevator System

Installation

Hydraulic systems are generally less expensive to install. Simpler equipment, lower infrastructure requirements, and no overhead machine room. For low-rise applications, this cost advantage can be significant.

Traction systems involve more sophisticated components, greater structural requirements, and more complex commissioning. The upfront cost difference between the two can be substantial, depending on building type and configuration.

Maintenance

Maintenance costs for both systems are broadly comparable over time, but the work differs. Hydraulic elevators require fluid and seal upkeep. Traction systems require rope, sheave, brake, and motor maintenance.

Understanding what your service agreement covers before committing is important.

Long-Term Value

This is where traction systems often justify their higher upfront cost in the right building. Lower energy consumption, longer service life, and compatibility with modernization upgrades give traction elevators a stronger long-term value proposition in high-use environments.

For low-rise buildings with moderate traffic, a well-maintained hydraulic system will serve reliably without the higher initial investment.

The true cost comparison depends on how the building is used, how much daily traffic the elevator handles, and how long the owner plans to operate the system. There is no formula that applies universally, which is why a site-specific evaluation matters.

Reach out to our team if you need your building evaluated

Traction vs Hydraulic Elevators Frequently Asked Questions

What is the difference between traction and hydraulic elevators?

To put it simply, traction elevators use an electric motor, steel ropes or belts, and a counterweight, while hydraulic elevators use a pump and fluid-driven piston. Traction systems suit taller, higher-traffic buildings and hydraulic systems are best for low-rise, lower-traffic applications, where simpler mechanics and lower cost are priorities.

Is a hydraulic elevator better than a traction elevator?

Neither is universally better. Hydraulic elevators are the right choice for low-rise buildings with moderate traffic and tighter budgets. Traction elevators are the right choice for taller buildings, high-traffic environments, and where energy efficiency and ride quality matter most.

Are hydraulic elevators cheaper than traction elevators?

Generally, yes. Hydraulic systems have lower upfront installation costs. However, traction systems can deliver better long-term value in the right building through lower energy use and longer service life. A full cost picture needs to account for building use, traffic volume, and ownership timeline.

Are cab sizes the same in hydraulic and traction elevators?

Cab dimensions are not determined by the drive system. They are determined by building code requirements, shaft dimensions, and intended use. Both systems accommodate a range of cab sizes. Your elevator contractor will size the cab based on your building’s needs and applicable local codes.

How can you tell if an elevator is hydraulic or traction?

A few indicators help identify the system:

  • Ride feel: Hydraulic elevators have a softer, slower acceleration. Traction elevators are typically smoother and faster.
  • Machine room location: Hydraulic machine rooms are at ground level or in the basement. Traditional traction machine rooms are at the top of the building.
  • Sound: Traction systems produce a mechanical, rope-driven sound. Hydraulic systems produce a distinct pump sound on ascent.

Are hydraulic elevators safe?

Yes, modern hydraulic elevators meet the same safety standards as traction systems. Advances in pump technology, seal engineering, and control systems have made them reliable and code-compliant. As with any elevator, proper installation and regular maintenance are what keep the system safe over its service life.

Do hydraulic elevators have counterweights?

No, hydraulic elevators do not use counterweights. The piston lifts the full weight of the cab on every upward trip. This is the primary reason hydraulic systems use more energy than traction systems, where the counterweight balances most of the load.

How high can a hydraulic elevator go?

Most conventional hydraulic systems are practical for up to about 50 to 60 feet of vertical travel, roughly five or six floors. Roped hydraulic configurations can extend this range somewhat. For taller buildings, a traction system is the more appropriate and cost-effective long-term solution.

Not Sure Which Elevator System Is Right for Your Building?

There is no one-size-fits-all answer. The right system depends on your building’s height, traffic patterns, infrastructure, and long-term goals as an owner. What works for a five-story condo is not the right call for a 20-story office tower.

Chicago Elevator works with building owners, developers, and property managers across Chicagoland and Northwest Indiana to evaluate options and recommend the right system for each project. Whether you are planning a modernization project or simply trying to understand your options before committing, we are here to help.

Reach out to request a quote or schedule a consultation, and we’ll give you  honest, straightforward guidance from our team that has been servicing Chicago’s buildings for over 50 years.

Blank silver closed elevator in office floor interior

Top Elevator Modernization Trends & Upgrades for 2026

In 2026, elevator modernization is shifting from fixing aging equipment to upgrading systems to meet new expectations for performance, energy efficiency, and connectivity. As building technology develops, elevators must keep pace to maintain safety, efficiency, and compliance with modern building codes. 

For building owners and property managers, keeping ahead of these trends is crucial. Strategic elevator upgrades not only improve dependability but also support long-term operating efficiency and occupant satisfaction. Elevator modernization trends are shaping building management in 2026, so it’s time to get informed.

4 Elevator Modernization Trends to Watch for in 2026

The elevator industry is rapidly evolving as buildings implement smarter infrastructure and more efficient systems. Modern technology aims to enhance performance, minimize downtime, and improve user experience.

Here are four key trends influencing modern elevator systems in 2026.

1. Connected Elevator Technology: The Rise of Automation

One of the major advancements in recent years is the growth of smart elevator technology powered by the Internet of Things (IoT).

The latest elevators use connected sensors, software platforms, and automated controls to monitor performance and optimize system operation.

These systems can:

  • Track usage patterns
  • Adjust dispatching to reduce wait times
  • Monitor equipment health in real time
  • Improve energy efficiency

Data and automation in smart systems reduce human error and enable earlier detection of potential issues. This increases reliability and enhances the passenger experience.

As buildings become more connected, smart elevator technology will play an increasingly important role in operations.

2. Energy-Efficient Upgrades: Sustainability at the Forefront

Energy efficiency is another major driver of elevator modernization in 2026.

Elevators account for a significant share of a building’s energy use, especially in high-rises. Rising energy costs and sustainability goals are prompting owners to invest in upgrades that reduce consumption without compromising performance.

Common modernization upgrades include:

  • Regenerative drive systems that capture and reuse energy
  • LED cab lighting upgrades
  • Modern variable-frequency motor drives
  • Improved standby power management

These upgrades lower operating costs and support sustainability initiatives. Over time, energy savings can help offset initial investments.

3. Touchless Technology & Contactless Controls

High-traffic buildings are increasingly adopting touchless elevator technology to improve hygiene and convenience. Touchless systems allow passengers to interact with elevators without physical contact through technologies such as:

  • Voice activation
  • Motion sensors
  • Smartphone-based elevator controls
  • Destination dispatch systems

These features are increasingly common in modern elevator systems, especially in offices, healthcare facilities, and hotels, where user experience and cleanliness are priorities.

4. Improved Data Analytics for Predictive Maintenance

Another major development in future elevator technology is the use of data analytics for predictive maintenance. Modern systems can continuously collect performance data from connected sensors. This information allows technicians to detect potential problems early, often before passengers notice any issues.

Predictive diagnostics can identify:

  • Motor performance irregularities
  • Door system wear
  • Controller errors
  • System performance anomalies

Early problem detection reduces emergency repairs, minimizes downtime, and ensures more consistent elevator performance.

5 Modernization Upgrades for Long-Term Performance in 2026

While trends shape the industry’s direction, successful modernization ultimately depends on the specific upgrades implemented within the elevator system. Strategic elevator upgrades can significantly improve performance, reliability, and efficiency for years to come.

Here are several modernization investments building owners should consider:

1. Replace Legacy Control Systems with Smart, Non-Proprietary Controllers

The elevator controller is the central component of the system. Many older buildings still use legacy control systems that are challenging to diagnose and maintain.

Replacing outdated controllers with modern, non-proprietary control systems is one of the most impactful modernization upgrades.

Modern controllers offer:

  • Improved diagnostics
  • Faster troubleshooting
  • More reliable system operation
  • Greater service flexibility

Non-proprietary systems reduce long-term reliance on a single manufacturer and provide greater flexibility in selecting service providers.

2. Retrofit for Energy Efficiency & Cost Savings

Energy-focused upgrades are among the most practical modernization investments available.

Upgrading older equipment with modern components can significantly reduce electricity consumption while improving system performance.

Common modernization retrofits include:

  • Regenerative drive installations
  • High-efficiency motor drives
  • LED lighting systems
  • Improved standby power management

These upgrades lower operating costs and increase environmental efficiency.

3. Integrate Smart Monitoring & Predictive Diagnostics

Modern elevator technology relies on connected monitoring systems that track performance in real time.

Smart monitoring upgrades include:

  • IoT-enabled sensors
  • Performance monitoring dashboards
  • Predictive diagnostic alerts
  • Remote troubleshooting capabilities

These tools allow technicians to detect issues earlier and respond faster when service is needed. Instead of reacting to breakdowns, maintenance teams can address problems before they disrupt building operations.

4. Upgrade Safety Systems to Meet 2026 Code Standards

Safety improvements are often a key reason buildings pursue elevator modernization.

Modernization can include upgrades such as:

  • Advanced door protection systems
  • Updated fire service controls
  • Improved emergency communication systems
  • Enhanced safety monitoring technology

Proactively upgrading safety components helps buildings stay compliant with current code requirements while reducing liability risks.

5. Improve Ride Quality & User Experience Through System Upgrades

Elevator modernization can also improve how elevators feel and perform for everyday users.

System upgrades can improve:

  • Door operation speed and reliability
  • Dispatch logic and passenger flow
  • Ride smoothness and vibration reduction
  • Leveling accuracy between floors

For many buildings, these improvements significantly enhance tenant satisfaction and overall building reputation.

The Future of Elevator Technology: What to Expect in 2026 & Beyond

Looking ahead, future elevator technology will continue to focus on automation, connectivity, and energy efficiency. Elevators are becoming more integrated with broader building management systems, allowing operators to monitor systems like HVAC, security, lighting, and elevators from a single platform.

As technology continues to evolve, buildings can expect smarter dispatch systems, improved connectivity, and more advanced predictive diagnostics that help identify potential issues before they cause downtime.

These advancements will make elevators more reliable, easier to manage, and better aligned with the operational needs of modern buildings and the people who rely on them every day.

Stay Ahead of Trends With Tried & True Elevator Experts

Keeping elevators reliable and up to date requires more than routine service. Strategic modernization helps ensure your elevator system remains safe, efficient, and prepared for evolving technology standards.

For building owners and property managers, planning modernization projects before equipment failures occur can reduce downtime, improve performance, and extend the life of elevator systems.

If you’re considering elevator upgrades or modernization options, our team can help you evaluate your current system and plan a modernization strategy that supports your building’s long-term needs.

Schedule a consultation with our expert team to discuss modernization planning and the right upgrade strategy for your building.

Modern Offices lobby interior area with elevators and stairs and with long reception desk

What Happens During an Elevator Modernization?

A Step-by-Step Guide for Building Owners

Elevator modernization is one of the most important, and most misunderstood, capital upgrades in a building. Owners often know their equipment is aging, unreliable, or failing inspection, but they’re unsure what modernization actually involves, how long it takes, or what tenants will experience.

If you’ve ever wondered what really happens behind the scenes, our guide will walk you through the elevator modernization process step by step, from first evaluation to final inspection.

What Is Elevator Modernization?

Elevator modernization is the process of upgrading or replacing outdated elevator components to improve safety, reliability, code compliance, ride quality, and long-term serviceability.

Modernization can range from targeted upgrades (like a new controller) to a full system overhaul. The right scope depends on your elevator’s age, condition, and performance history, as well as your building’s needs and limitations.

Why Building Owners Choose to Modernize

Most modernization projects are driven by one or more of the following issues:

  • Frequent breakdowns and service calls
  • Difficulty finding parts for obsolete equipment
  • Failed inspections or code compliance concerns
  • Long wait times or poor ride performance
  • Tenant complaints
  • Rising maintenance costs

Modernization is not just about fixing what’s broken; it’s about extending the useful life of your elevator system, while improving safety and reliability.

What Building Owners Gain from Modernization

When completed, modernization delivers the following benefits:

  • Improved reliability and fewer breakdowns
  • Easier access to replacement parts
  • Enhanced safety and code compliance
  • Better ride quality and performance
  • Updated cab appearance
  • Lower long-term maintenance risk

Most importantly, modernization gives owners predictability, with fewer emergency repairs and more control over operating costs.

The Elevator Modernization Process: Step by Step

Here’s our detailed guide to the elevator modernization process, so you can understand every step of the process:

Step 1: System Evaluation & Condition Survey

Every modernization starts with a detailed assessment. During this step, an elevator contractor will inspect:

  • Controller and electrical systems
  • Door operators and mechanical components
  • Fixtures and cab interiors
  • Safety devices and code compliance items
  • Machine room and hoistway conditions

They’ll review maintenance history, shutdown frequency, and part availability to determine which components should be upgraded vs. replaced.

Outcome: A modernization proposal outlining scope, priorities, and budget options.

Step 2: Engineering & Project Planning

Once the scope is approved, the project moves into the planning phase, which includes:

  • Engineering design for new equipment
  • Code compliance review (ASME A17.1 and local Illinois/Chicago requirements)
  • Scheduling to minimize building disruption
  • Ordering long-lead components

At this stage, owners receive a project timeline, typically ranging from several weeks to a few months depending on scope and number of elevators.

Outcome: Finalized project plan, with costs and an installation schedule.

Step 3: Permits & Pre-Construction Preparation

Before work begins, required permits must be secured; this may involve:

  • Submitting plans to the authority having jurisdiction
  • Coordinating inspection requirements
  • Scheduling shutdown windows

Your contractor will also coordinate with building management as needed to notify tenants, plan elevator downtime, and ensure safe work areas

Outcome: Elevator modernization work is approved and ready to begin.

Step 4: Elevator Shutdown & Equipment Removal

Modernization requires taking the elevator out of service, so technicians can begin removing outdated components, such as:

  • Old controllers and relay panels
  • Door operators and door equipment
  • Signal fixtures and wiring
  • Obsolete safety devices

Crews work in the machine room, hoistway, pit, and inside the cab during this step. This means building owners and tenants will experience noticeable construction activity and temporary service reduction, especially in single-elevator buildings.

Step 5: Installation of New Equipment

This is where the transformation happens and new components are installed, such as:

  • Microprocessor-based controllers for improved reliability
  • New door operators for smoother, faster door performance
  • Updated wiring and traveling cables
  • Modern fixtures, buttons, and indicators
  • Code-required safety upgrades

During this step, all equipment is installed to meet current safety standards and manufacturer specifications.

Outcome: The elevator has a modern control and operating system in place.

Step 6: Cab & Interior Upgrades (If Included)

Many modernization projects also include aesthetic improvements, which come in the final phase of the project. These types of upgrades can involve:

  • New wall panels and finishes
  • Updated lighting systems (often LED)
  • New ceilings and handrails
  • Flooring replacement
  • New operating panels and displays

While simply cosmetic, these upgrades improve tenant perception and property value.

Step 7: Testing & Adjustments

Before the elevator can return to service, extensive testing is required. To ensure the finished product is working as expected, technicians perform:

  • Door operation adjustments
  • Ride quality and leveling checks
  • Speed and stopping accuracy tests
  • Safety circuit verification

The goal is to ensure the system operates smoothly, reliably, and in full compliance with code.

Step 8: Safety Testing & Final Inspection

Modernized elevators must pass required safety tests and inspections before being placed back into service. This may include:

  • Category testing as required by code
  • Witnessed inspections by the authority having jurisdiction
  • Documentation review

Only after passing inspection can the elevator legally return to operation.

Outcome: The elevator is approved, compliant, and back in service!

Step 9: Turnover, Training, & Ongoing Maintenance

After completion, the elevator contractor provides the building owner with documentation for new equipment, maintenance recommendations, and warranty information.

Most importantly, modernized elevators require regular preventive maintenance to protect your investment and maximize lifespan, so once the turnover process happens, be sure to set up an ongoing maintenance program for your elevator too.

How Long Does the Elevator Modernization Process Take?

Timelines vary depending on scope and building type, but a single elevator modernization typically takes several weeks from shutdown to completion. Multi-elevator buildings may have projects phased to keep some cars in service during this period.

Overall the shutdown period will be worth the potential inconvenience, and planning helps reduce tenant disruption and maintain accessibility until the project is completed.

Work With Experts Who Know the Elevator Modernization Process

A successful modernization depends on detailed planning, code knowledge, and experienced technicians who understand both older equipment and modern systems, which means choosing the right elevator company is pivotal to your modernization project running smoothly.

Chicago Elevator manages modernization projects from initial evaluation through final inspection, ensuring work is code-compliant, well-coordinated, and built for long-term performance. We stay on top of modernization trends, so you don’t have to.

Remember: if your elevators are aging, unreliable, or facing increasing violations, modernization may be the most cost-effective long-term solution.

Ready to Explore Elevator Modernization for Your Building?

We can evaluate your current system, explain your options clearly, and provide a step-by-step modernization plan tailored to your property, so you can understand the best approach and timeline for your building’s needs.

Schedule a modernization assessment today and get expert guidance you can trust!